Stormwater
Tunnel
|
Length:
|
9.7km
|
|
|
Diameter:
|
11.7m
|
|
|
Storage
Capacity:
|
1,000,000 cubic meter
|
|
|
Tunneling
Method:
|
Tunnel Boring Machine (TBM)
|
|
|
Origin
of Tunneling Technology:
|
Germany
|
|
|
TBM
Type:
|
Slurry Shield
Largest in South East Asia & 2nd Largest
in Asia
|
|
|
 |
Motorway
Tunnel
|
Length:
|
3 km
|
|
|
Structure
type:
|
Double Decker
|
|
|
Ingress
and Egress
Connections' Length :
|
1.5km at Jalan Sultan Ismail.
1.4km at Jalan Tun Razak.
1.6km at KL-Seremban Highway.
|
|
|
Links:
|
Connects city centre near
Kampung Pandan roundabout to KL-Seremban Highway
near Sungai Besi.
|
|
|
 |
Storage
Resevoir
|
Location:
|
Ex-mining pond in Taman Desa
|
|
|
Surface
Area:
|
22 ha ( 216 594 sq m)
|
|
|
Storage
Capacity:
|
1,400,000 cubic metres
|
|
|
 |
Holding
Basin
|
Location:
|
Kampung Berembang
(behind Gleneagles Hospital in Jalan Ampang)
|
|
|
Surface
Area:
|
10 ha (104 008sq m)
|
|
|
Storage
Capacity:
|
600,000 cubic metres
|
|
|
|
|
|